Construction stages of timber frame houses

The construction of a timber frame house lasts from 3 to 7 months, depending on the size of the project, the complexity of the project and the chosen assembly and finish. A fully completed 120 m2 residential timber frame house with built communications can be constructed in 3 to 4 months.


1Architects3-150x150

First stage

The most suitable project for a typical “North House” is chosen, as well as an individual building project can be developed for the customer. A contract is signed for the design and construction of the house and the design works are commenced.


20150610_111105-150x150

Secondstage

When the project for the house is ready and approved, construction works on the site begin: foundation construction, including supply of a communications system to the house, construction of sewerage networks, installation of heated floors and lying of concrete floors.


20150610_1158411-150x150

Thirdstage

Besides the construction of foundations for houses, wall, ceiling and roof panels are also manufactured in the factory. Windows and panels are placed in vehicles for transportation.


CAM01006-150x150

Fourth stage

The transport of panels to the object is organised and the panel assembly process is performed. It lasts 1-3 days, depending on the project.


20150724_173147-150x150

Fifthstage

When the house assembly process is completed, the roofing and facade decoration works are followed. In parallel, the construction of internal communications is carried out: electricity, water, sewerage, heating and interior plasterboard decoration.


DSC_0250-150x150

Sixthstage

All interior finishing works are done: wall plaster and putty, painting, wallpaper hanging, wall and floor tiling, installation of interior stairs, floor finishing, interior door installation.


CAM01189-150x150

Seventhstage

Fencingconstruction, cobblestone laying and territory improvement works are performed.